Transpennine Route Upgrade team looks back on milestones reached on the project in 2025

As the year ends, the Transpennine Route Upgrade (TRU) team has been looking back on the progress made on the project over the past 12 months.

The TRU is a multi-billion-pound railway programme that is set to transform journeys across the North by providing more frequent, faster and greener rail journeys between Manchester, Huddersfield, Leeds and York.

The team was out on the railway over the festive season making the most of the quieter period to keep progress moving.

Engineers have been realigning tracks and installing new signalling equipment in Mirfield, continued with the Huddersfield Station roof canopy restoration and began the demolition of Whitacre Street overbridge in Deighton.

The TRU team has achieved several milestones on the project in 2025placeholder image
The TRU team has achieved several milestones on the project in 2025

Key milestones in 2025 include:

Forty miles of track was installed.

12,000 train services were sent via diversionary routes, following a £100m investment, keeping customers on trains and on the move.

Thirty miles of cable roughing was laid for signals.

A total of 7,721 shifts were worked by the customer team, supporting passengers in getting to where they need to be.

£800m was spent with local businesses.

1,000 OLE foundations were constructed, facilitating electric trains along the route in the future.

James Richardson, managing director for the Transpennine Route Upgrade, said: “This year has produced so many achievements and what we're doing across the programme will not just improve journey times and reliability, but better connect towns and cities across the North.

“TRU is a key enabler to unlock potential in our communities and support regional economic growth, and we are looking forwards to another successful year in 2026.”

Huddersfield remained a key area for the programme. Engineers installed new bridge beams across span one of Huddersfield viaduct, reconfigured platforms and completed track and signalling upgrades to improve reliability and prepare the station for longer trains in the future.

A new £46m train maintenance centre opened at Hillhouse depot in October, built to keep trains running for customers across Yorkshire.

More than 5,000 people were at work on the project by the end of 2025, with more than 10,000 people now trained at its dedicated safety training centre and more than 400 apprenticeships filled on the programme.